dc dotCreds
Florida Air Conditioning Contractor Examination (Class A & Class B)

Florida HVAC Contractor Practice Test

Start today’s free 10-question Florida HVAC Contractor set with source-backed explanations, local progress, and a fresh rotation every morning.

10 Free Daily Questions Source-backed Explanations 200 Verified Questions

Questions updated at Sep 7, 2026, 6:49 PM CDT

Go Pro - One Time Unlock

Unlock the full Florida HVAC Contractor bank

200 verified questions Exam Mode Practice Mode Detailed explanations Weak-area review No subscription - one-time unlock

Get the complete source-backed bank with Interview Questions, the full Study Guide, full Course Notes, detailed explanations, weak-area review, and exam-style practice.

Interview Questions Full Study Guide Full Course Notes Exam Mode Practice Mode Guided Course Detailed explanations Weak-area review No subscription
$4.99 One-time payment
See bundle and PDF options

We will confirm your site email in one quick checkout step.

Why DotCreds?

Practice with explanations that teach.

Source links for every answer Every wrong answer explained Guided Course included Practice and Exam Mode Weak-area tracking Same verified bank across web practice

What you get with free practice

10 Free Questions Daily Fresh set every day from the live bank
Detailed Explanations Learn with clear source-backed answers
Track Your Progress Daily history and performance insights
Upgrade Anytime Unlock the full bank when you are ready
Today's 10 Florida HVAC Contractor questions

Use this Florida HVAC Contractor practice test to review Florida Air Conditioning Contractor Examination Class A and Class B. Questions rotate daily and each answer links back to the source used to write it.

Today’s Set
10 questions
Rotates at 10:00 AM local time
Progress
0/10
Answered on this page
Accuracy
0%
Loading countdown…

200 verified questions are in the live bank. Free daily questions are selected from a rotating sample set. Unlock Pro to access the full question bank.

Preparing today’s free questions... Ordering the final locked-bank set before showing the practice cards.
Question 1 of 10
Objective Specific exam blueprint requirement: repair leaks and piping — Concept: repair leaks and piping (Item 141) Maintenance Service of Refrigeration and HVAC Systems

A leak is found at a brazed copper joint. After recovering refrigerant and repairing the joint, what should happen before evacuation and recharge?

Concept tested:
Question 2 of 10
Objective Specific exam blueprint requirement: evaluate building-envelope effects — Concept: evaluate building-envelope effects (Item 186) Energy Management

A west-facing glass wall has a much higher solar heat gain than the original glazing. The HVAC unit is unchanged. What effect should be evaluated?

Concept tested:
Question 3 of 10
Objective Specific exam blueprint requirement: select controls, motors, compressors, pumps and boilers — Concept: select controls, motors, compressors, pumps and boilers (Item 21) Pre-Installation

A boiler-replacement schedule lists three pumps with the same design flow but different head capabilities. Which information is essential before the contractor selects the pump?

Concept tested:
Question 4 of 10
Objective Specific exam blueprint requirement: apply EPA refrigerant-handling requirements — Concept: apply EPA refrigerant-handling requirements (Item 161) Maintenance Service of Refrigeration and HVAC Systems

A technician recovers refrigerant from one owner's system and plans to use it in a different owner's equipment without reclamation. What regulatory concept matters?

Concept tested:
Question 5 of 10
Objective Specific exam blueprint requirement: install systems across tonnage ranges — Concept: install systems across tonnage ranges (Item 52) Installation of Refrigeration and HVAC Systems

A certified Florida Class B air-conditioning contractor is bidding a packaged cooling project whose single system is rated 18 tons. No other scope issue is present. Which statement correctly applies the statutory capacity limit?

Concept tested:
Question 6 of 10
Objective Specific exam blueprint requirement: install centrifugal and absorption systems — Concept: install centrifugal and absorption systems (Item 81) Installation of Refrigeration and HVAC Systems

A centrifugal chiller's motor starter and machine nameplate data do not match the available electrical service. What should happen before energization?

Concept tested:
Question 7 of 10
Objective Specific exam blueprint requirement: service air-distribution equipment — Concept: service air-distribution equipment (Item 152) Maintenance Service of Refrigeration and HVAC Systems

A VAV box is over-supplying its zone even at minimum command. The actuator linkage slips and the damper never reaches the commanded position. What is the best repair?

Concept tested:
Question 8 of 10
Objective Specific exam blueprint requirement: plan rigging, structural loads and mechanical equipment placement — Concept: plan rigging, structural loads and mechanical equipment placement (Item 22) Pre-Installation

A crane pick for an air handler is planned over an occupied walkway. The unit's approved lifting points and weight are known. What is the best control before the lift?

Concept tested:
Question 9 of 10
Objective Specific exam blueprint requirement: diagnose airflow, refrigerant and electrical faults — Concept: diagnose airflow, refrigerant and electrical faults (Item 131) Maintenance Analysis of Refrigeration and HVAC Systems

A three-phase compressor hums and trips quickly. One incoming phase has zero voltage while the other two are normal. What is the most direct fault category?

Concept tested:
Question 10 of 10
Objective Specific exam blueprint requirement: calculate thermal resistance using R and U factors — Concept: calculate thermal resistance using R and U factors (Item 4) Pre-Installation

A contractor is comparing two wall assemblies for a Florida HVAC load calculation. The proposed assembly has an overall U-factor of 0.05 Btu/h·ft²·°F. Before entering the assembly into the load model, what overall R-value should be used?

Concept tested:
Locked preview

You are viewing today’s free 10. Unlock 190 more questions.

Unlock full bank
Daily sample Rotating practice Free daily questions are selected from a rotating sample set.
Pro bank Full access Unlock Pro to access the full question bank, Exam Mode, Practice Mode, and random tests.
Florida HVAC Contractor Pro $4.99 one-time

Unlock all 200 Florida HVAC Contractor questions, explanations, review tools, and exam-style practice.

50 Exam Practice Test $1.99 one-time

A 50-question Florida HVAC Contractor PDF for short review sessions. Questions come first, then the answer review and explanations later in the file.

All Access $6.99/month

Unlock every active practice exam, bundle and path experience, Pro course and study content, and included downloads.

What’s includedEvery current and future active practice exam, All active bundle and career-path practice content, Pro course lessons, study content, and supported paid downloads

Choose an unlock option to continue. We will confirm your site email in one quick checkout step.

Secure checkout powered by Stripe. Source-backed questions. Not brain dumps. Checkout stays on this page and unlocks the same Pro builder on this practice page.

Purchase options

Unlock the full Florida HVAC Contractor bank.

Get the full bank, Exam Mode, Practice Mode, question sets, random tests, readiness tracking, saved box scores, and review tools for this exam.

The PDF versions keep questions first and move the answer review, explanations, and distractor notes to the back of the file.

200 verified exam-style questions Every choice explained Exam Mode and Practice Mode Question sets and random tests Readiness score and trends Previous test box scores

You've answered 0/10 questions in today's set.

Locked: 190 more questions in the full bank.

Locked: exam simulation mode, practice mode, readiness tracking, and saved review history.

Checkout stays on this page, so you can keep practicing, unlock the full bank, and start Exam Mode or Practice Mode when you are ready.

Cheat Sheets

7-day score keeper

Answer questions today and this will become a rolling 7-day scorecard.

Local history
Optional progress sync

Keep today’s practice moving

Guest progress saves automatically on this device. Add an email later when you want a magic link that keeps your daily Florida HVAC Contractor practice in sync across browsers.

Guest progress saves on this device automatically

Guest progress is available without an account.

Source-backed answer review

The free daily Florida HVAC Contractor set includes crawlable question text, answer choices, correct answer labels, objective mapping, and source links. Only the first SEO card includes answer explanations and any extra learning features. Pro-only bank questions stay locked; this section mirrors only the 10 free daily questions already shown on this page.

Question 1 A leak is found at a brazed copper joint. After recovering refrigerant and repairing the joint, what should happen before evacuation and recharge?

Answer choices

  1. A. Charge immediately because a new braze is automatically leak-free.
  2. B. Pressure-test with oxygen because it provides faster bubble formation.
  3. C. Pressure/leak test the repaired system with an appropriate inert test gas and method within equipment pressure limits, then evacuate if tight.
  4. D. Run the compressor while the system is open to draw air through the repaired joint and treat that action as the corrective basis for the maintenance record.

Correct answer

Pressure/leak test the repaired system with an appropriate inert test gas and method within equipment pressure limits, then evacuate if tight.

Leak repair is more than sealing the visible hole: recover/isolate refrigerant appropriately, repair using the correct fitting/brazing process, eliminate the root mechanical cause, and verify tightness before evacuation/recharge. Applied here, pressure/leak test the repaired system with an appropriate inert test gas and method within equipment pressure limits, then evacuate if tight.

Wrong-answer review

  • A. Charge immediately because a new braze is automatically leak-free.: Incorrect. Brazed repairs should be verified before evacuation and charging.
  • B. Pressure-test with oxygen because it provides faster bubble formation.: Incorrect. Oxygen under pressure around oil/brazing is hazardous.
  • D. Run the compressor while the system is open to draw air through the repaired joint and treat that action as the corrective basis for the maintenance record.: Incorrect. Operating an open refrigeration system introduces contamination and can damage equipment.

Extra learning features

Why candidates miss this

Candidates often miss this by anchoring on a familiar shortcut instead of the measured or stated condition. The decisive clue is the leak has been repaired but the system has not yet been evacuated. Pressure/leak-test with an appropriate dry inert gas within component limits before evacuation and recharge; never use oxygen. Likely wrong answer: Pressure-test with oxygen because it provides faster bubble formation. Review focus: U.S. EPA — Section 608 Stationary Refrigeration Service Practice Requirements

Interview question

Q: After repairing a refrigerant leak at a brazed joint, how do you prove the system is ready for evacuation? Strong answer: After the repair and with refrigerant properly recovered, I would pressure/leak-test the repaired circuit with dry nitrogen or another appropriate inert gas using a rated regulator and staying within the equipment/component test-pressure limits. Once the repair passes the leak test, I would release the test gas safely, evacuate with a micron gauge, then recharge and verify operation. Oxygen is never an acceptable refrigeration pressure-test gas.

  • dry nitrogen/inert gas
  • rated regulator
  • component test-pressure limits
  • leak verification
  • evacuation after test
  • no oxygen

Caution: Avoid vague language such as 'pressurize to operating pressure'; the test pressure must follow the equipment/service procedure and ratings.

Why this matters

A repaired joint must be proven leak-tight before evacuation and charging. A controlled dry-inert-gas test catches an incomplete repair while the system is still empty, preventing refrigerant loss and repeat service.

Objective/domain: Maintenance Service of Refrigeration and HVAC Systems

Source: U.S. EPA — Section 608 Stationary Refrigeration Service Practice Requirements

Question 2 A west-facing glass wall has a much higher solar heat gain than the original glazing. The HVAC unit is unchanged. What effect should be evaluated?

Answer choices

  1. A. Only heating load changes; solar gain cannot affect cooling.
  2. B. Higher afternoon cooling load and zone imbalance, using the new fenestration properties and orientation in the load analysis.
  3. C. No load change because HVAC load depends only on floor area.
  4. D. Lower cooling load because glass always has less heat gain than insulated wall and carry that assumption into the final load or efficiency documentation.

Correct answer

Higher afternoon cooling load and zone imbalance, using the new fenestration properties and orientation in the load analysis.

Question 3 A boiler-replacement schedule lists three pumps with the same design flow but different head capabilities. Which information is essential before the contractor selects the pump?

Answer choices

  1. A. Only the pump motor voltage, because electrical compatibility determines hydraulic performance.
  2. B. Only the boiler input rating, because pump head is proportional to burner input.
  3. C. Only the pipe diameter at the pump discharge, because diameter determines the correct pump size and carry that assumption through the final design calculation and submittal.
  4. D. The system's required flow and total dynamic head at the design condition, checked against the pump curve.

Correct answer

The system's required flow and total dynamic head at the design condition, checked against the pump curve.

Question 4 A technician recovers refrigerant from one owner's system and plans to use it in a different owner's equipment without reclamation. What regulatory concept matters?

Answer choices

  1. A. Refrigerant becomes exempt from EPA requirements once it is placed in a recovery cylinder.
  2. B. Adding virgin refrigerant to recovered refrigerant automatically makes the mixture reclaimed.
  3. C. Recovered refrigerant can always be transferred between owners if it looks clear in a sight glass and use that repair approach before returning the equipment to normal service.
  4. D. Recovered refrigerant that changes ownership generally must be reclaimed to the applicable purity standard before resale/reuse across owners, subject to EPA rules.

Correct answer

Recovered refrigerant that changes ownership generally must be reclaimed to the applicable purity standard before resale/reuse across owners, subject to EPA rules.

Objective/domain: Maintenance Service of Refrigeration and HVAC Systems

Source: U.S. EPA — Section 608 Stationary Refrigeration Service Practice Requirements

Question 5 A certified Florida Class B air-conditioning contractor is bidding a packaged cooling project whose single system is rated 18 tons. No other scope issue is present. Which statement correctly applies the statutory capacity limit?

Answer choices

  1. A. The system is within Class B scope only if its heating section is permanently disabled and no ventilation work is included.
  2. B. The system exceeds Class B scope because any packaged cooling system above 15 tons requires a Class A air-conditioning license.
  3. C. The system exceeds Class B scope because Class B contractors may install cooling equipment only in residential occupancies.
  4. D. An 18-ton cooling system is below the Class B limit of 25 tons in any one system, so this capacity alone does not exceed Class B scope.

Correct answer

An 18-ton cooling system is below the Class B limit of 25 tons in any one system, so this capacity alone does not exceed Class B scope.

Objective/domain: Installation of Refrigeration and HVAC Systems

Source: 2026 Florida Statutes §489.105 — Contractor definitions and scopes

Question 6 A centrifugal chiller's motor starter and machine nameplate data do not match the available electrical service. What should happen before energization?

Answer choices

  1. A. Energize briefly and use measured current to decide whether the voltage mismatch is acceptable.
  2. B. Resolve the electrical-service and starter compatibility against the equipment nameplate, approved design and applicable electrical requirements before startup.
  3. C. Bypass overload protection for the first startup so nuisance trips do not interrupt commissioning and record that configuration in the startup and turnover documentation.
  4. D. Raise protective-device settings until the motor reaches full speed.

Correct answer

Resolve the electrical-service and starter compatibility against the equipment nameplate, approved design and applicable electrical requirements before startup.

Objective/domain: Installation of Refrigeration and HVAC Systems

Source: Florida DBPR — Air A Contractors General Trade Knowledge Examination Content Information

Question 7 A VAV box is over-supplying its zone even at minimum command. The actuator linkage slips and the damper never reaches the commanded position. What is the best repair?

Answer choices

  1. A. Raise the zone cooling setpoint so the excess airflow is less noticeable and treat that action as the corrective basis for the maintenance record.
  2. B. Partially block the diffuser with cardboard and leave the faulty linkage.
  3. C. Reduce central fan speed until that one zone reaches design.
  4. D. Repair/adjust the actuator and linkage, calibrate the damper position/airflow control, then rebalance the terminal if needed.

Correct answer

Repair/adjust the actuator and linkage, calibrate the damper position/airflow control, then rebalance the terminal if needed.

Objective/domain: Maintenance Service of Refrigeration and HVAC Systems

Source: Florida DBPR — Air A Contractors General Trade Knowledge Examination Content Information

Question 8 A crane pick for an air handler is planned over an occupied walkway. The unit's approved lifting points and weight are known. What is the best control before the lift?

Answer choices

  1. A. Establish the lift plan and exclusion zone, verify rigging capacities and pick points, and keep personnel clear of the suspended-load path.
  2. B. Allow pedestrians to pass beneath the load if the crane operator maintains radio contact.
  3. C. Use any convenient cabinet opening as a tag-line attachment even if the manufacturer prohibits it and document that approach in the coordinated mechanical design package.
  4. D. Increase hoisting speed so the suspended-load exposure time is shorter.

Correct answer

Establish the lift plan and exclusion zone, verify rigging capacities and pick points, and keep personnel clear of the suspended-load path.

Question 9 A three-phase compressor hums and trips quickly. One incoming phase has zero voltage while the other two are normal. What is the most direct fault category?

Answer choices

  1. A. A dirty evaporator coil, because low airflow opens an electrical phase.
  2. B. An oversized TXV, because valve position determines line voltage.
  3. C. An electrical phase-loss/supply problem that must be corrected before attempting further compressor operation.
  4. D. A refrigerant undercharge, because low charge removes one phase of voltage and use that conclusion to guide the remaining diagnostic measurements.

Correct answer

An electrical phase-loss/supply problem that must be corrected before attempting further compressor operation.

Objective/domain: Maintenance Analysis of Refrigeration and HVAC Systems

Source: Florida DBPR — Air A Contractors General Trade Knowledge Examination Content Information

Question 10 A contractor is comparing two wall assemblies for a Florida HVAC load calculation. The proposed assembly has an overall U-factor of 0.05 Btu/h·ft²·°F. Before entering the assembly into the load model, what overall R-value should be used?

Answer choices

  1. A. R-40, because the reciprocal must be doubled for cooling calculations.
  2. B. R-20, because overall thermal resistance is the reciprocal of the overall U-factor.
  3. C. R-0.05, because R and U use the same numerical value.
  4. D. R-10, because the reciprocal must be divided by two for walls and document that approach in the coordinated mechanical design package.

Correct answer

R-20, because overall thermal resistance is the reciprocal of the overall U-factor.

Where to go after the daily web set

How are Florida HVAC Contractor questions generated?

dotCreds builds Florida HVAC Contractor practice questions from public exam objectives and Florida DBPR exam and documentation references. The questions are written for realistic study practice, not copied from exam dumps.

How are explanations sourced?

Each question includes an explanation and, when available, a source link back to the provider documentation or reference used to validate the answer. That keeps the practice tied to study material you can actually review.

What score do I get?

The page tracks today's answered count and accuracy for the 10-question daily set, then saves a 7-day score history on this device so you can see your recent practice trend.

Why use this site?

The site is the fastest way to start Florida HVAC Contractor practice without installing anything. It is built for daily recall, quick weak-topic discovery, and source-backed explanations you can review immediately.